In Supplier Back Scheduling, planning starts from a fixed delivery deadline and works backward: to meet that deadline, an order must be released to the supplier by time X to allow them sufficient lead time for their own procurement, production, and shipment.
Source: https://www.leanproduction.com/back-scheduling.html